![rovalec travaux ssr richaud](https://www.rovalec.com/wp-content/uploads/2023/08/rovalec-travaux-ssr-richaud-1024x768.jpeg)
![projet rovalec ssr richaud](https://www.rovalec.com/wp-content/uploads/2023/08/projet-rovalec-ssr-richaud-1024x768.jpeg)
![projet ssr richaud rovalec](https://www.rovalec.com/wp-content/uploads/2023/08/projet-ssr-richaud-rovalec-1024x768.jpeg)
![hopital projet rovalec](https://www.rovalec.com/wp-content/uploads/2023/08/hopital-projet-rovalec-1024x768.jpeg)
![projet ssr hopital richaud rovalec](https://www.rovalec.com/wp-content/uploads/2023/09/projet-ssr-hopital-richaud-rovalec-1024x768.jpeg)
![rovalec projet ssr richaud](https://www.rovalec.com/wp-content/uploads/2023/09/rovalec-projet-ssr-richaud-1024x768.jpeg)
![hopital ssr richaud projet rovalec](https://www.rovalec.com/wp-content/uploads/2023/09/hopital-ssr-richaud-projet-rovalec.jpeg)
![fils electriques rovalec projet](https://www.rovalec.com/wp-content/uploads/2023/11/fils-electriques-rovalec-projet-1024x768.jpeg)
![panneaux electriques rovalec](https://www.rovalec.com/wp-content/uploads/2023/11/panneaux-electriques-rovalec-1024x768.jpeg)
![projet hopital ssr richaud rovalec](https://www.rovalec.com/wp-content/uploads/2023/11/projet-hopital-ssr-richaud-rovalec-1024x768.jpeg)
![projet rovalec electricite](https://www.rovalec.com/wp-content/uploads/2023/11/projet-rovalec-electricite-1024x768.jpeg)
![Ssr richaud projet rovalec](https://www.rovalec.com/wp-content/uploads/2023/11/Ssr-richaud-projet-rovalec-1024x768.jpeg)
![WhatsApp Image 2024-04-18 at 18.53.54 copie](https://www.rovalec.com/wp-content/uploads/2024/04/WhatsApp-Image-2024-04-18-at-18.53.54-copie-1024x768.jpeg)
![WhatsApp Image 2024-04-18 at 18.53.58 (1) copie](https://www.rovalec.com/wp-content/uploads/2024/04/WhatsApp-Image-2024-04-18-at-18.53.58-1-copie-1024x768.jpeg)
![WhatsApp Image 2024-04-18 at 18.53.57 (1) copie](https://www.rovalec.com/wp-content/uploads/2024/04/WhatsApp-Image-2024-04-18-at-18.53.57-1-copie-1024x768.jpeg)
![WhatsApp Image 2024-05-15 at 10.04.06 (1)](https://www.rovalec.com/wp-content/uploads/2024/06/WhatsApp-Image-2024-05-15-at-10.04.06-1-1024x768.jpeg)
![WhatsApp Image 2024-05-15 at 10.04.04](https://www.rovalec.com/wp-content/uploads/2024/06/WhatsApp-Image-2024-05-15-at-10.04.04-1024x768.jpeg)
![WhatsApp Image 2024-05-15 at 10.04.03](https://www.rovalec.com/wp-content/uploads/2024/06/WhatsApp-Image-2024-05-15-at-10.04.03-1024x768.jpeg)
![WhatsApp Image 2024-05-15 at 10.04.02](https://www.rovalec.com/wp-content/uploads/2024/06/WhatsApp-Image-2024-05-15-at-10.04.02-1024x768.jpeg)
![WhatsApp Image 2024-06-26 at 09.18.32 (1)](https://www.rovalec.com/wp-content/uploads/2024/07/WhatsApp-Image-2024-06-26-at-09.18.32-1-1024x768.jpeg)
![WhatsApp Image 2024-06-26 at 09.18.30](https://www.rovalec.com/wp-content/uploads/2024/07/WhatsApp-Image-2024-06-26-at-09.18.30-1024x768.jpeg)
Description du projet
Ce projet porte sur le réaménagement complet des niveaux 2 et 3 (36 chambres) du bâtiment + la détection incendie des niveaux SS1, SS2, RdC et Combles.
Travaux réalisés en milieu occupé.
DÉTAILS DU PROJET
NOM DU CLIENT : CH de Versailles
BUDGET : 440 000 €
SUPERFICIE : 1 500 m²
DÉBUT : Avril 2023
FIN : Juin 2024
EN COLLABORATION AVEC :
ARCHITECTE : UNHI
BET : Gruet Ingénierie
- 180 mètres de chemin de câble
- 50 mètres de goulotte PVC
- 800 prises de courant
- 350 luminaires et 20 BAES
- 4 armoires divisionnaires
- 140 mètres de chemin de câble
- 200 prises informatique cât. 6a
- Système d'appel malade
- 8 lecteurs de badge
- Distribution TV, 40 prises
- 244 DAI + 20 DM - SSI
- 152 indicateurs d'actions - SSI
- 8 AGS + 8 avertisseurs flash - SSI
Détails du projet
- Nom du client :CH de Versailles
- Date d'achèvement:3 août 2023
- Budget :440 000 €
- Superficie : 1500 m²
- Début : Avril 2023
- Fin : En cours
- En collaboration avec :
- Architecte : UNHI
- BET : Gruet Ingenierie